With Mash Direct in the planning stage of building a new factory facility they ask BL to design and cost new chill and freezer rooms as part of their extension plan. The design included a loading bay area, a dispatch room and a freezer room all to be installed on a 20- week programme.

The design included 3 systems for dispatch and 2 systems in the loading bay and freezer room. A competitive price ensured BL won the contract and the works commenced on site.

All equipment was installed and commissioned to programme to the satisfaction of the client.

Project summary

Project name Mash Direct New factory extension
End user Mash Direct
Consultant in house
Main Contractor Mash Direct

Equipment

Loading Bay

2 off Bitzer LHV7E/4DE-7.F3Y-405
2 off LUVE E45HC 4731 E6

Dispatch

3 off SCM FRIFO MCV B200 BT
3 off LUVE F62HC 2208R 6 CAB.TR

Freezer Room

2 off SCM FRIFO MCV B300 BT
2 off LUVE LS62H 6406 E10 RES-BOC+JB.A-IS

Back to News

Unit B2
Sydenham Business Park
17 Heron Road
Belfast
BT3 9LE

t: 028 9045 3325
e: info@blgroup.co.uk

SafeContractor-Roundel-R-293x300.png refcom.png Constructionline Gold quality-environmental-logos.png