Mash Direct - Blast Chill

Posted: 4/7/2018

With Mash Direct in the process of building a new product handling facility they came under serious pressure to increase production to keep up with an ever-increasing order book. They approach BL to supply and install an additional blast chill capable of 580kg/hr.

Normally requiring a 12-week programme the equipment was designed, purchased, installed and commissioned in just 4 weeks.

Project Summary

Project Name: Mash Direct Blast Freeze 9
End user:  Mash Direct
Consultant: In house
Main Contractor: None
Equipment: Searle CCU050-RDM